Text Box: NEW WATER TANK

 

 

 

 

 

 

 

 

On November 13, 2008 three bids were received with a low bid at $3,085,000.  The contract was awarded to Landmark Structures (www.ldmkusa.com).  Construction will resume April 2010, with a completion date scheduled for December 2010 (weather permitting). We are pleased to announce the project qualified for the American Response Recovery Act (ARRA) stimulus funds. The already low 2% loan along with the 20% principal forgiveness will save an estimated $663,873.00 in borrowing costs.

The combination of a welded steel tank and reinforced concrete support pedestal is the most efficient use of materials for both containment and support, providing the lowest capital and life cycle cost.  Once finished, we will be proud to have constructed this signature tank that will be a geographic marker and an enduring symbol of community pride.